The rooftop solar power system was installed at the Haksan Vi Na Co., Ltd. factory with a capacity of 632.4 kWp. The project officially went into operation in 2026.
Haksan Vi Na Co., Ltd. is a 100% South Korean-invested enterprise specializing in the manufacturing and processing of sports shoes for export. With a desire for sustainable development, the company is actively implementing renewable energy solutions at its factory located in Quarter 3, Hoa Loi Ward, Ho Chi Minh City.
The system utilizes 1,020 high-efficiency Jinko 620 Wp solar panels and 4 Huawei inverters (three 150 kW units and one 50 kW unit). With an optimal design, the system is expected to generate approximately 850,000 – 900,000 kWh of clean electricity annually, helping to reduce emissions by more than 575 tons of CO2 per year and contributing to greenhouse gas emission reductions for the factory.
By installing a self-consumption solar power system, Haksan Vi Na can:
Utilize available roof space to maximize the value of the manufacturing facility.
Confidently focus on core business operations and meet energy demands with a high-
efficiency PV system that provides electricity at a lower cost than the grid.
Strengthen its commitment to sustainable development by using green energy,
minimizing carbon emissions during the production process, and meeting the sustainability requirements of customers.
With this system, Haksan Vi Na Co., Ltd. will utilize a lower-cost solar power source for factory operations and production. Utilizing renewable energy through the ELA model helps Haksan Vi Na maintain cash flow autonomy for other operational activities, meet criteria for green production, and digitize the emissions reduced by the factory, thanks to an effective monitoring and measurement system.